Bulk reset due date - Limiting Continue pop-ups

I have a record set of 7000 items that I need to reset the due date. I am having to say “Continue” to every item that has a block on it. Is there a way around that? Thanks.

The only thing I can think of that would be similar would be the "Suppress breakable links when deleting,” but I doubt those permissions would help here.

I do wonder if maybe you were resetting the due dates from a branch that was less likely to encounter so many blocks, for example, a technical services branch that didn’t have so many blocking conditions set if that might also help.

The only other thing I can think of would be using something like AutoHotKey to wait for the pop-up window and then click Continue for you.

Overall, it sounds like a good Idea Exchange enhancement request too.

1 Like

Sounds like autohotkey is the only option that would work in this case but I’ve never used that so I’ll look into it. Thank god when I’m deleting en masse I can deselect the breakable and unbreakable links. Thanks!